Name of work
LSTK of Balance of Plant (BoP) package for 2 X 350 MW Coastal Thermal Power Project.
Site
Krishnapatinam,Andhra Pradesh, India
Client
M/s. CCCL-EDAC Energy Ltd., Chennai.
Customer
M/s. Meenakshi Energy Private Ltd., Noida ( GDF Suez)
Project Duration
30 Months
Our Scope of Work
| Design, Engineering, Supply and Erection of Balance of Plant (BoP) Packages |
| - Coal Handling Package |
| - Ash Handling Package |
| - Water System package (CW & ACW, WTP) |
| - Fire Detection & Protection System |
| - Heat Ventilation & Air Conditioning System |
| - Piping |
| - Induced Draft Cooling Tower |
| - Fuel Oil Handling System |
| - Electrical Balance of Plants (E-BoP) & Switchyard |
| - Associated Control & Instrumentation works |
Date of Completion
Ongoing