• Dhahran Road - Al Nada Neighborhood - First National Group Tower - Dammam

MECHANICAL PROJECTS

Name of work
Mechanical Erection of Boiler Unit-I and BoP Equipments for Lara Super Thermal Power Plant Project (800MW x 2 Unit).

Site
Lara Village, Raigarh district, Chhattisgarh, India.

Client
M/s. Doosan Power Systems India Pvt Ltd

Customer
M/s. NTPC Ltd.

Project Duration
36 Months

Our Scope of Work
- Boiler & its Auxiliaries
- BoP Equipment erection

Date of Completion
Ongoing
Name of work
Mechanical Erection of Boiler Unit II for Kudgi Super Thermal Power Plant Project stage - I (800MW x 3 Unit).

Site
Kudgi Village, Bijapur district, Karnataka, India

Client
M/s. NTPC Ltd.

Customer
M/s. Doosan Power Systems India Pvt Ltd

Project Duration
36 Months

Our Scope of Work
- Boiler & its Auxiliaries

Date of Completion
Ongoing
Name of work
PACKAGE-A: Mechanical Erection of Boiler & its auxliaries of 1 x 660 MW unit # 3 including auxiliary boiler for 2x660 MW units at IBV TPS, Banharpalli, Odisha

Site
Banharpalli, Odisha, India

Client
M/s. BHEL-PSER

Customer
M/s. IB Valley TPS Ltd (Orissa Power Generation corporation Ltd)

Project Duration
36 Months

Our Scope of Work
- Boiler & its Auxiliaries

Date of Completion
Ongoing
Name of work
Mechanical Erection works of Boiler and its Auxiliaries, ESP for Unit- 1 (Package-A), TG and its Auxiliaries, CW and ACW system (Package A) and Power Cycle Piping works of 2 x 500 MW New Neyveli Thermal Power Project.

Site
Neyveli, Cuddalore District, Tamil Nadu, India.

Client
M/s. BHEL- PSSR

Customer
M/s. Neyveli Lignite Corporation Ltd, Chennai

Project Duration
Boiler Package: 34 Months TG Package : 20 Months PCP Package: 26 Months

Our Scope of Work
- Boiler & Its Auxiliaries , ESP (Unit-I)
-  TG & its Auxiliaries (Unit-I)
- CW & ACW systems (for Unit-I & II)
- Power Cycle Piping works (Unit-I)

Date of Completion
Ongoing
Name of work
Mechanical Erection, Testing & Commissioning of Boiler & its Auxiliaries for 1 x 350 MW KVK Nilachal Power Project

Site
Cuttack, Odisha, India

Client
M/s. KVK Nilachal Power Pvt. Ltd.

Customer
M/s. KVK Energy and Infrastructure Pvt. Ltd., Hyderabad

Project Duration
18 Months

Our Scope of Work
Boiler and Auxiliaries, ESP

Date of Completion
Ongoing
Name of work
Mechanical Erection, Testing & Commissioning of Boiler for 1 x 150 MW Nagai Power Project

Site
Nagapattinam, Tamil Nadu, India

Client
M/s. NCC Ltd

Customer
M/s. KVK Energy and Infrastructure Pvt. Ltd., Hyderabad (KVK Nagai Power Ltd)

Project Duration
17 Months

Our Scope of Work
Boiler and Auxiliaries, ESP

Date of Completion
Ongoing
Name of work
Mechanical Erection, Testing & Commissioning of TG & its auxiliaries for 1 x 150MW Nagai Power Project

Site
Okkur Village, Nagapattinam, Tamil Nadu, India

Client
M/s. KVK Nagai Power Private Limite

Customer
M/s. KVK Nagai Power Private Limited

Project Duration
9 Months

Our Scope of Work
TG & its Auxiliaries

Date of Completion
Ongoing
Name of work
R and M works of ESP Unit-II, III and IV of 5 x 200MW Singrauli Thermal Power Station.

Site
Singrauli, Uttar Pradesh

Client
BHEL - Power Sector Northern Region

Customer
NTPC Ltd

Project Duration
18 Months

Our Scope of Work
R and M works of ESP and auxiliaries

Date of Completion
Ongoing
Name of work
Mechanical Erection,Testing and Commissioning of Boiler & its auxiliaries, ESP for 1 x 525 MW set at Tuticorin TPS Stage IV, Megha Engineering and Infrastructures Limited (MEIL)

Site
Tuticorin, Tamil Nadu

Client
M/s. BHEL- PSSR

Customer
M/s. Megha Engineering and Infrastructures Limited (MEIL)

Project Duration
Boiler and its Auxiliaries : 26 Months ESP: 24 Months

Our Scope of Work
Boiler and Auxiliaries
ESP

Date of Completion
Ongoing

eg.jpg
Name of work
Mechanical Erection,Testing and Commissioning of STG and its auxiliaries for 2 x 660 MW, Stage-II, NTPC Tanda Thermal Power Project

Site
Tanda, Uttar Pradesh

Client
M/s. Alstom Bharat Forge Power Pvt. Ltd

Customer
M/s. NTPC Ltd

Project Duration
26 Months

Our Scope of Work
Steam Turbine Generator & its auxiliaries, Piping works (Unit-I and II)

swiss replica watches


Date of Completion
Ongoing
Name of work
Mechanical Erection,Testing and Commissioning of Boiler & its auxiliaries of 1 x 270MW (Unit #4), for 4 x 270 MW Bhadradri Thermal Power Project at Manuguru. Site Manuguru, Telangana

Site
Manuguru, Telangana

Client
M/s. BHEL-PSWR

Customer
M/s.TS Genco

Project Duration
17 Months

Our Scope of Work
Boiler and its auxiliaries

Date of Completion
Ongoing

ELECTRICAL AND CONTROL & INSTRUMENTATION PROJECTS

Name of work
Electrical Package of Unit-I & II, 2x525MW Malibrahmani Thermal Power Project (Monnet)

Site
Angul, Odisha, India

Client
M/s. BHEL - PSSR, Chennai

Customer
M/s. Monnet Power

Project Duration
12 Months

Our Scope of Work
Erection & installation of Electrical items, Laying of cables, Cable Trays, Panels, etc.,

Date of Completion
Ongoing
Name of work
Electrical works for Unit 1 and Auxiliary Boiler, Unit 2 of 2 x 500 MW New Neyveli Thermal Power Project

Site
Neyveli, Tamil Nadu

Client
M/s. BHEL-PSSR, Chennai

Customer
M/s. NLC India Limited

Project Duration
26 Months

Our Scope of Work
Electrical works for Unit 1 and Auxiliary Boiler, Unit 2

Date of Completion
Ongoing

make.py

TRANSMISSION & DISTRIBUTION

Name of work
Rural electrification works involving 11KV & LT Lines at Gosani block in Gajapati district Odisha under RGGVY

Site
GAJAPATI District, GOSANI block in Odisha

Client
BENZFAB Technologies Pvt Ltd

Customer
NTPC / NSIC

Project Duration
7 months

Our Scope of Work
- Site Survey, Planning, Design, Engineering, Supply of Equipments &   Installation     works for Rural Electrification works  in Gosani Block
- 11KV Tranmsission lines - 26 KM , LT Lines - 463.5KM
- Installation of Distribution Transformers
- Providing service connection to BPL consumers, etc.,

Date of Completion
Ongoing - 2018
Name of work
Supply, Erection, Testing and commissioning of (i) 132/33kV SS at Kotagiri, (ii) 132KV DC/SC line, (iii) 132kV Bay extension at 132/33kV SS Jakora in Nizamabad District

Site
Kotagiri, Nizamabad district & Jakora Nizamabad District

Client
M/s. ICoat Project Pvt. Ltd

Customer
M/s. TSTRANSCO, Ltd

Project Duration
12 months

Our Scope of Work
(i) 132/33kV SS at Kotagiri, Nizamabad District
(ii) 132KV DC/SC line (16km) from 132/33kV Jakora Substation to Proposed Kotagiri SS,
(iii) 132kV Bay extension at 132/33kV SS Jakora in Nizamabad District

Date of Completion
on going